This project takes place in an operational facility which must remain operational during construction. The project consists of six (6) Elements: Stormwater Management, Traffic Control, Work by other City Vendors, Landscape / Hardscape, Improvements and Repairs, and Striping. This project may be built in two phases. The first phase would complete all the underground piping, conduits, storage basing, etc.; while the second phase would consist of the above-ground work. A critical part of the scope of work is the completion of a specified portion of the project by October 1, 2016
Central Los Angeles Recycling and Transfer Stations (CLARTS) Storm water and Safety Improvements
Work Order:
SRCLSTSF
Contract:
C-126694
Location:
2201 E. Washington Blvd, Los Angeles, CA 90021
Total Contract Amount:
$7,956,000.00
Notice to Proceed & Duration:
12/01/2015; 255 Working Days